Crane made it up the driveway without a problem at 0845. Let the work begin. The temps were only about 27, continually cloudy, light snow occasionally, steady light breeze for Jonas, Kyle, Corey, John and Doug plus the crane driver. We have about 4" of snow on the ground with ice underneath in places where trucks and the forklift have been. Last Sunday Paul tried to hack away the deeper ruts but made little progress so today he moved driveway rocks with the tractor for about an hour to make landing pads in front and in back of the house to help the forklift stay steady. That will be a job for the landscapers to repair.
First The Crew did the entire back, then the front except for the dormers. The crane has other work tomorrow so the dormer panels will have to be lifted by forklift. They are smaller so that shouldn't be a problem.
The roof panels are 20' long and 4' wide so each lift covered a lot of exposed roof, but it was still a lot of work. The back roof took 11 panels. They weigh a (figurative) ton, maybe 300-400 lbs.
Each lift required 2 brackets of 2x4s to be screwed into the panels at balanced points near each end. The lifting straps were threaded through and then the crane operator lifted the panel to the exact point the men on the roof needed. They caulked and cranked the locking cams, removed the brackets and were ready to prepare the next one. All the panels were labeled like the rest of the house.
The crew was here from 8:00-5:00. I think they are as anxious as we are to get the house enclosed but for different reasons perhaps.
I finalized the plumbing fixtures with Ted at Crescent this afternoon. I hope that 4.5' bathtub upstairs will be enjoyed because it's the most expensive fixture in the house.