Chris finished the trim around the hearth but will put some quarter round on the back splash tiles later. This softens the edge and toe-stubbing factor.
Mike the painter has filled all the wood work nail holes and is now putting on the finish coats on the windows and the initial coat on the folding doors at the laundry.
Doug applied MinWax Spar varnish and stain to the cherry vanity, shelf, and trim for the powder room. The pieces are drying up in the loft on the window seat. The difference in the color of the local cherry and the Ft. Washington cherry is amazing. We'll have to ask Findley about that. The varnish really makes the end wood darker and stand out so the dovetails show better.
Bill plugged the basement railings, oiled them, and caulked the trim baseboards at the landing.

John and Chris finished off the closet shelving and hanging poles: guest closet with one rod and shelves, laundry with bifold doors, and the master closet with 4 rods and floating shelves.
Scott and Julian have added some more 1 ft tiles in the shower, have applied the 1 inch glass tiles to complete the 6 inch stripe around the remaining wall and inside the soap cubby as well as put a diamond of glass tiles on the bench seat.
We had a nice thunderstorm here around 1030 with some good thunder; Buddy was shaking so Paul sat next to him and he calmed down.
Paul put out some fertilizer on the fruit trees and some of the thermal cover evergreens before the rains came and also threw down some buckwheat seeds next to the asparagus.